    Most "commercial solar" quotes doing the rounds in India are either suspiciously cheap or padded with line items you don't need. Here's a transparent breakdown for a real-world 30 kWp rooftop system on an Indian SME site - the size most shops, clinics, small offices, showrooms and workshops actually end up at.

    Why 30 kWp is the typical sweet spot

    Almost every state DISCOM keeps a non-domestic LT commercial category (LT-3 / LT Cat 3A / LT-II depending on the state) that a 30 kWp plant fits comfortably inside. That means:

    • You stay on the LT tariff (no HT conversion, no CT/PT metering)
    • Net metering goes through the standard LT 1Φ/3Φ bi-directional meter
    • Sanctioned load of 25-50 kW typically supports a 30 kWp plant without breaching the system size ≤ sanctioned load rule that nearly every state's net-metering regulation carries

    Above 50 kWp things change in most states - electrical inspectorate (CEIG/CEI) certification, structural drawings to the DISCOM, longer review cycles. 30 kWp keeps you on the fast path.

    Installed cost: Rs 18-21 lakh, line by line

    For Tier-1 hardware, properly installed, anywhere in urban India in 2026:

    Line item Cost (₹)
    Mono PERC / TOPCon panels (54 × 555 Wp) 6,40,000 – 7,20,000
    String inverter (25–30 kW, Tier-1) 2,40,000 – 3,00,000
    Galvanised mounting structure 1,20,000 – 1,50,000
    DC + AC cabling, MC4, conduits 80,000 – 1,10,000
    ACDB / DCDB, SPDs, isolators, earthing, LA 70,000 – 90,000
    Net-metering compatible meter + DISCOM fees 35,000 – 50,000
    Civil work, transport, installation labour 1,80,000 – 2,40,000
    Liaisoning, drawings, commissioning 60,000 – 80,000
    Monitoring (Wi-Fi/4G data logger) 25,000 – 40,000
    GST and contingency 2,50,000 – 3,20,000
    All-in ₹18,00,000 – ₹21,00,000

    That's roughly ₹60,000-₹70,000 per kWp all-in. Anything materially below ₹50,000/kWp usually means swapped BoS, downrated panels, or a no-show inverter brand.

    What the system actually generates

    Specific yield across most of India runs 1,400-1,650 kWh per kWp per year - the higher end in Gujarat, Rajasthan, Telangana, Karnataka and Maharashtra, the lower end in the eastern and north-eastern states. Taking a mid-band site at ~1,550:

    • Annual generation: ~45,000-47,000 units
    • Monthly average: ~3,800 units

    The savings math

    Commercial LT tariffs in 2026, with fixed and energy charges combined, land around ₹8.5-₹11/unit in most states for SMEs in the relevant slab. Using ₹10/unit:

    • Energy displaced: ~46,000 units × ₹10/unit = ₹4.6 lakh/year
    • Net of ₹15,000-₹20,000/year in cleaning + minor AMC
    • Net annual benefit: ~₹4.4 lakh

    Payback

    • System cost: ₹19.5 lakh (midpoint)
    • Net annual benefit: ₹4.4 lakh
    • Simple payback: 4.5 years
    • With accelerated depreciation (40% in year 1, on the depreciable cost): payback effectively compresses to 3.5-4 years for profitable businesses
    • Without AD: 5-6 years, and still 19-20 years of near-free power after

    What we won't compromise on at this size

    • ALMM List-I panels with BIS certification
    • Tier-1 inverter with a service centre in or near your city
    • Hot-dip galvanised structures (not painted MS - it rusts inside 4 years)
    • Original Stäubli MC4 connectors
    • Remote monitoring from day one

    If your quote doesn't itemise these, you're not comparing apples to apples.

    Free assessment

    Get a free 30 kWp commercial assessment

    Share your roof and bill details - we'll send back system sizing, expected savings and a payback estimate within 24 hours.

    We reply within 24 hours. No spam - your details are only used for this enquiry.